On the morning of Thursday 21st Jan, two new concrete beams for the downstream deck will be installed.
These have been manufactured off-site and, at 35 tonnes each, will need to be lifted using two cranes in tandem. Once the beams are in place, the new concrete deck can be built on top and the services transferred from the upstream side, which then frees up the upstream deck for demolition. Access to Mill Row & Bridgend will be maintained throughout.
Bridge renovation is on target for completion by May 2016.